Improving Royal Oak

Construction Project Updates


The city realizes construction will be an inconvenience and all efforts to expedite the work will be utilized to minimize traffic conflicts and access to various properties abutting the project. If you have questions you can contact the Engineering Division at 248.246.3260.

2018 Project Map

CAP2007 Gardenia Avenue Improvements

East of Main Street to Campbell Road

Contractor: AJAX Paving Industries, Inc.


The roadwork is complete except for lane striping. The road has been opened at Main Street and at all side streets. The curved portion of Gardenia at Campbell Road will remain closed until striping is installed. The striping is scheduled to be installed soon, though the crew must wait for temperatures above 40°F to place the striping.

CAP1806 S. Campbell Road Resurfacing

10 Mile Road to 11 Mile Road

Contractor: Iafrate Construction Company


The west half of S. Campbell Road is closed for second phase of construction, and traffic is currently shifted to the east side of the road. One lane is open in each direction. The following left turns are not allowed during this phase of construction:

  • Northbound and southbound Campbell Road at 11 Mile Road
  • Eastbound Lincoln Avenue at S. Campbell Road
  • Northbound and southbound Campbell Road at Lincoln Avenue

During the week of October 22nd, the contractor plans to install new curbing between Lincoln and 11 Mile Road. The contractor also plans to install storm sewer and perform concrete pavement repairs between 10 Mile Road and Lincoln throughout the week.
 
The contractor hopes to complete this project prior to the winter, however, the weather in the coming weeks will determine if this is possible. If necessary, the remainder of the project could be delayed until the spring.  

You can find more information on the project at romi.gov/campbellroad

CAP1505 Concrete Street Repairs

Contractor: Galui Construction Company, Inc.


For the week of October 22nd, the contractor plans to finish pouring the remaining halves of streets for the entire project by the end of the week. The contractor will then work on back-filling and miscellaneous repair work from the previous streets.


Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.