Improving Royal Oak

Construction Season Begins


The city realizes construction will be an inconvenience and all efforts to expedite the work will be utilized to minimize traffic conflicts and access to various properties abutting the project. If you have questions you can contact the Engineering Division at 248.246.3260.

2018 Project Map

CAP1806 S. Campbell Road Resurfacing

10 Mile Road to 11 Mile Road


This project is currently being bid through the Michigan Department of Transportation.  Construction is tentatively scheduled to begin towards the end of May.

CAP1808 N. Main Street Resurfacing

11 Mile Road to Gardenia Avenue

Contractor: Pro-Line Asphalt Paving Corp.


This project is scheduled to begin during the first week of May.  The contractor will shift traffic to the east side of the road, with one lane open in each direction.  Access to all businesses will be maintained throughout the project.

CAP1815 Asphalt Resurfacing Improvements

Contractor: AJAX Paving Industries, Inc.


The project is divided into three phases:

CAP1815 Phasing

The contractor is working on Phase 1 streets.  The contractor will be finishing the curb removals and replacements on N. Vermont Avenue, and will begin work on N. Blair Avenue and N. Altadena Avenue during the week of April 30th.

CAP1835 Road Reconstruction Improvements

Contractor: Hard Rock Concrete, Inc.


Woodland Avenue - Webster Road to Glenwood Road

The contractor has completed installation of the water main on Woodland Avenue.  The contractor will be performing pressure testing and bacteria testing of the water main the week of April 30th to ensure the water main is safe for public use.  After all testing is approved, the contractor will connect the new water main pipe to the city’s water system.  The connections typically require the water to be turned off for about four to eight hours, and residents will be notified of any water shutoffs 24 hours in advance with a door hanger.

Bonnie View Drive - Lloyd Avenue to Northwood Boulevard

The contractor has paved the west side of Bonnie View which is currently closed to traffic, and has begun removing the pavement on the east side of the road. The contractor tentatively plans to place concrete on the east half of the road during the week of April 30th, likely towards the end of the week.

Yorba Linda Boulevard - Fairlawn Avenue to Springer Avenue

The contractor is scheduled to begin pavement removals starting on April 27th.  The contractor will remove half of the roadway pavement to allow for water main installation.  One lane of pavement will be left in place for local traffic while the water main is constructed.


Parkway Drive - Normandy Road to Woodward Avenue

The contractor has poured the south/east side of the roadway and this pavement will be closed to vehicles through the week of April 30th.  The contractor will begin pavement removals on the other half of the roadway later in the week.

Linwood Avenue - Webster Road to Glenwood Road

No work to begin until school is out for the summer.


Delaware Avenue - E. Kenilworth Avenue to E. Harrison Avenue

No work yet; the contractor tentatively plans to begin the work in late June or July.

CAP1505 Concrete Street Repairs

Contractor: Galui Construction Company, Inc.


The contractor will be saw-cutting the project streets starting in May.  Pavement removals and concrete pavement will not begin until late May or early June.  

CAP1822 Non-Motorized Improvements


The city will be installing signage and striping for a north-south bike route through the city.  The bike route begins at Washington Avenue and 10 Mile Road, extends north to Euclid Avenue, then east to N. Main Street, and finally north the city limits.  Where there are currently four lanes of traffic, the street will be reduced to a 3-lane roadway, with one lane of traffic in each direction, a center turn lane, and bicycle lanes on each side of the road.  This project is expected to begin in June.


Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.

You can visit www.romi.gov/currentprojects to view the 2018 project map, find copies of mailed construction notices, and read about the city's various construction projects.