CAP1735 Road Reconstruction Improvements
Contractor: Mark Anthony Contracting, Inc.
Batavia Avenue
The contractor has placed the bottom course of asphalt along Batavia Avenue and is planning to complete topsoil and sod restoration work during the week of October 9th. In order to keep the final pavement surface clean, the final top course of asphalt will be placed after restoration is complete.
Dallas Avenue
The contractor plans to place topsoil and sod after restoration on Batavia Avenue is complete.
Lockwood Avenue
Lockwood Avenue is now open to traffic. The contractor replaced driveway approaches and sidewalk on Saturday, which will remain closed for approximately one week.
Consumers Energy has several flags of sidewalk to be replaced as part of the gas service work. Restoration will take place once the other project streets are completed.