Improving Royal Oak

Completed Streets

Many city projects are substantially complete, except for restoration. Several contractors have begun restoration and will continue throughout the month.

CAP1735 Road Reconstruction Improvements

Contractor: Mark Anthony Contracting, Inc.


Batavia Avenue

The contractor plans to pave Batavia with asphalt on Wednesday September 27th. Residents will be able to access their driveways during the paving work, but there may be slight delays while waiting for equipment to move. Sod restoration work is tentatively scheduled for the following week.
  

Dallas Avenue

The contractor will place the remaining concrete at Lenox and Stephenson today and also the driveway approaches for the church. The remaining driveway approaches and sidewalk on Dallas are scheduled to be poured on September 29th.

Lockwood Avenue

The contractor plans to finish removing the road and will place the stone road base early during the week of September 25th. Concrete placement for the roadway is tentatively scheduled for the end of that week.
 
The contractor is finishing placement of topsoil on the completed streets, and plans to wait until the weather cools down in another week before placing sod.

CAP1630 Special Assessment Paving Improvements

Contractor: Mark Anthony Contracting, Inc.


Public Alley - 14 Mile Road to Rochester Road (behind businesses)

The contractor has scheduled milling of the asphalt within the driveways and parking lot for Wednesday September 27th. The parking lot will be paved in two phases on Thursday and Friday to allow half the lot for parking each day.

Orchard Grove Drive

The road is now open to traffic. The contractor has scheduled driveway and sidewalk replacements for Friday September 29th.
 
The contractor is finishing placement of topsoil on the completed streets, and plans to wait until the weather cools down in another week before placing new sod and replacing dead sod from earlier in the summer.

CAP1505 Concrete Street Repairs

Contractor: Galui Construction Co., Inc.


The contractor will begin work on Hickory, Marais and Galpin Avenue during the week of September 25th. The contractor has several punch-list items on various streets, which will be addressed after the remaining three streets have been completed.


CAP1702 Sidewalk Improvement Program

Contractor: Italia Concrete Construction, Inc.


If you would like to sign up for the Payment Plan, instead of receiving a one-time full invoice, the deadline is September 30, 2017. Sign up forms are available at the Engineering counter at city hall or at www.romi.gov/sidewalks


Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.

You can visit www.romi.gov/currentprojects to view the 2017 project map, find copies of mailed construction notices, and read about the city's various construction projects.