Improving Royal Oak

Completed Streets

Many city projects are substantially complete, except for restoration. The city allows contractors to wait until after Labor Day for grass restoration to allow for more favorable weather conditions.

CAP1735 Road Reconstruction Improvements

Contractor: Mark Anthony Contracting, Inc.


Batavia Avenue

The contractor plans to mill the asphalt roadway on Monday September 11th. The road will still be accessible to traffic.

Later in the week, the contractor plans to replace the concrete road base in areas where utility work was performed. Short sections of the road may be closed to allow for this work, with access from the cross streets available for residents.
 
Once the concrete road base is placed and cured, the contractor will install the hot mix asphalt for the roadway, likely in the next couple weeks.

  

Dallas Avenue

The contractor will be replacing the removed driveway approaches and sidewalk between Helene and Lenox during the week of September 11th.

The concrete roadway from Lenox to Stephenson Highway will be removed during the week, and storm sewer will be installed. The contractor tentatively plans to pour the new pavement during the week of September 18th.

Fairview Avenue

The contractor will be replacing driveway approaches on Fairview Avenue on Friday September 8th. Restoration will follow within a few weeks.

Kalama Avenue and Brinkey Avenue

The contractor plans to work on restoration for these streets in the coming weeks.

There are several flags of sidewalk that were removed by Consumers Energy for the gas main work and Consumers Energy is responsible for replacing this concrete.

Lockwood Avenue

The water main work is now complete and the contractor plans to install storm sewer during the week of September 11th. The roadway is tentatively scheduled to be paved later in the week of September 18th.

CAP1630 Special Assessment Paving Improvements

Contractor: Mark Anthony Contracting, Inc.



Public Alley - 14 Mile Road to Rochester Road (behind businesses)

The contractor plans to mill the driveway lanes and parking lot on Monday September 8th. The parking lot will still be open for business parking. The asphalt is scheduled to be replaced later in the week.  Paving will be done in two phases to allow half of the lot to remain open for parking at all times.


Orchard Grove Drive

The contractor tentatively plans to pour the new roadway pavement at the end of the week of September 11th. Once paved, the road will remain closed to traffic for approximately one week to allow the concrete to cure.

CAP1505 Concrete Street Repairs

Contractor: Galui Construction Co., Inc.


The contractor plans to return to the city later this month to work on Hickory, Marais and Galpin Avenue.


CAP1702 Sidewalk Improvement Program

Contractor: Italia Concrete Construction, Inc.


If you would like to sign up for the Payment Plan, instead of receiving a one-time full invoice, the deadline is September 30, 2017. Sign up forms are available at the Engineering counter at city hall or at www.romi.gov/sidewalks


Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.