Improving Royal Oak

CAP1715 Asphalt Resurfacing Improvements

Contractor: AJAX Paving Industries, Inc.


The contractor will continue placing topsoil and seed on Phase 1 and 3 streets, and will move to Phase 2 streets afterward. The contractor will water the restored areas throughout the summer until grass is established. Residents are encouraged to water the seeded areas as well.
 
Milling has been completed on Phase 4 streets. The contractor will be performing road base repairs during the week of July 10th, and tentatively plans to complete paving on these streets at the end of the week.
CAP1715 Phases

CAP1735 Road Reconstruction Improvements

Contractor: Mark Anthony Contracting, Inc.


Batavia Avenue

The contractor will continue water main connections and water service transfers to the new water main during the week of July 10th. Properties that will be without water during connections will be notified via door hanger the day beforehand. Shutdowns are typically 4 to 8 hours long.
  

Dallas Avenue

The contractor tentatively plans to begin work on Dallas Avenue the week of July 17th.

Fairview Avenue

The contractor will finish road preparation work once Consumers Energy replaces an existing shallow gas main, likely during the week of July 10th.

Kalama Avenue and Brinkey Avenue

The contractor plans to begin underground utility installations on Kalama Avenue between Brinkey Avenue and Stephenson Highway starting on Monday July 10th. The remainder of the pavement will be removed on Kalama Avenue and Brinkey Avenue after utility work is completed. 
 
Residents will receive door-hanger notices 24 hours in advance when driveways will be unavailable.

CAP1630 Special Assessment Paving Improvements

Contractor: Mark Anthony Contracting, Inc.


Public Alley - East of Rochester Road, from Whitcomb Ave. to Millard Ave.

The majority of work is completed. The contractor will place topsoil and sod in disturbed areas in the coming weeks.


S. Edison Avenue and W. Park Avenue

The contractor plans to joint-seal the new pavement in the next couple weeks, and will post “No Parking” signs for this one-day operation.

The contractor plans to place concrete for driveway approaches and sidewalk during the week of July 10th.

Wrenford Road, Massoit Road, Bassett Road, Girard Road

Sod has been placed on Wrenford Road, Massoit Road, Basset Road and part of Girard Road. The remaining sod of Girard Road is scheduled for the week of July 10th.

The contractor will water the restored areas until the sod takes root. Residents are encouraged to water the sodded areas as well.

Public Alley - 14 Mile Road to Rochester Road (behind businesses)

The contractor tentatively plans to begin work in the alley the week of July 10th.

Orchard Grove Drive

The contractor tentatively plans to begin water main work the last week of July.

CAP1535 Road Reconstruction Improvements

Contractor: Hard Rock Concrete, Inc.


Sherman Drive Construction

Sherman Drive is now open to traffic. The city plans to install the remaining “No Parking” and street signs along Sherman Drive in the next few weeks. Sod restoration is planned for September.

Linwood Avenue Construction

The contractor plans to pour the east half of Linwood Avenue the week of July 10th. Once all roadway concrete has been placed, the road will remain closed to all traffic for one week while the concrete cures.

Residents have been authorized to park in the Shrine Grade School parking lot as needed during construction.

CAP1710 Water Main Improvements

Contractor: F.D.M. Contracting, Inc.


Bellaire Avenue

The contractor has placed all concrete on the north side of the roadway, and plans to begin preparing the replacement areas on the south side of the road during the week of July 10th.


Rochester Road

All concrete repairs are completed. The contractor tentatively plans to begin asphalt replacement for driveways the week of July 17th.

CAP1505 Concrete Street Repairs

Contractor: Galui Construction Co., Inc.


The contractor will be working on the second half of the streets north of 12 Mile Road for the next two to three weeks. Work on Galpin, Hickory and Marais will be delayed until August.

2017 Sidewalk Improvement Program

Contractor: Italia Construction, Inc.


The contractor plans to finish sidewalk work on major roads during the week of July 10th, and plans to start new sidewalk installation (where none previously existed). More information on the program can be found at www.romi.gov/sidewalks.

Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.