2025 Sidewalk Program
The contractor is finishing work in the Phase 1 section on the west side of Woodward. Then they will be moving to the Phase 2 section, working west to east between Normandy and 14 Mile Road. Crews will be saw-cutting and removing sidewalk squares, and pouring new cement. Landscape crews will follow afterwards to backfill any holes, clean up any materials or debris, and restore lawn damage with topsoil and seed.
If driveway access will be affected, residents will receive a door hanger notice the day beforehand.
Work along major roads and half-mile roads will be done at the end of the project.
Schedule:
- Phase 1: Working east to west between 13 Mile Road and Normandy Road
- Phase 2: Working west to east between Normandy Road and 14 Mile Road
- Phase 3: Working west to east between 14 Mile and north city limits.
If property owners wish to discuss the proposed sidewalk replacement with the project inspector, please call 248.246.3260 to schedule an appointment.