CAP2410 Water Main Improvements
All water main installation and connections are complete for both streets, only roadwork is remaining.
On Northwood & Sycamore, the contractor has begun milling the existing asphalt off the roadways, beginning with westbound Northwood, followed by eastbound Northwood, finishing with Sycamore. Once complete they will begin paving the first layer of asphalt on the roadways.
The contractor is also finishing up miscellaneous concrete work along the corridor.
The landscaping restoration and sprinkler repairs will be completed over the next few weeks.