Improving Royal Oak
2023 project map

2023 Construction Project Map available now!

Use the map above to see if a project is affecting your street. The city realizes construction will be an inconvenience and all efforts to expedite the work will be utilized to minimize traffic conflicts and access to various properties abutting the project.

Notices of Construction have been mailed to affected residents and copies are available online here.

CAP2306 Rochester Road

This week the contractor is continuing work on the east side of the roadway. All pavement has been removed and the contractor is placing the new aggregate road base and curb & gutter this week and grading.

Turn Restrictions and Closures:

Left turns will not be allowed for northbound and southbound traffic at 12 Mile Road, Girard Avenue and at 13 Mile Road during construction to avoid backups. Northbound Rochester Road will be completely closed between Gardenia Avenue and Dewey Street. Local access to the Oakview Cemetery and Rite Aid will remain open.

More information about the lane conversion can be found at: www.romi.gov/RochesterRoad

CAP2308 Major Road Improvements


Vinsetta Boulevard:

This week, the contractor is milling the existing road pavement on Vinsetta, scheduled for Monday and Tuesday. Once complete the contractor will be road testing and doing measurements to prepare for grading and paving next week.

Normandy Road:

Construction and water main installation has been delayed to the week of May 15th.

Normandy Road will be closed to thru traffic throughout construction. Residents with driveways on Normandy will still be able to enter the construction zone via the side streets to access their property. Businesses should direct their patrons, employees and deliveries to use Coolidge to access Normandy Road to minimize conflicts with construction work.

Lincoln Avenue:

The road is closed to thru traffic, but access to businesses and residences will remain open. The contractor has completed concrete work and tentatively plans to mill the roadway surface the week of May 15th.

CAP2305 Concrete Repair Program

The contractor is progressing with work in the Phase 1 & Phase 2 areas with second halves. The contractor will also begin removals in the Phase 3 neighborhood with plans to pour the new pavement towards the end of week/beginning of next week.

Work will only be performed on one side of the street at a time, to maintain access for residents throughout construction. Only the worst sections of concrete pavement will be removed and replaced, not the entire roadway. If driveway access will be affected, residents will be notified the day beforehand via doorhanger.

The map below shows the project streets highlighted in LIGHT BLUE.

CAP2305 map excerpt

CAP2310 Water Main Improvements

 Water main installation is complete on Longfellow. Minimal work will be visible this week, as bacteria testing and pressure testing occurs on the new main. Once complete, the contractor will begin final water main connections.

CAP2315 Asphalt Resurfacing

The project streets shown in purple on the project map have been divided into three phases as shown below.

Phase 1

On Hawthorn, the contractor is continuing work, most of the concrete on the south side of the roadway is now complete and the contractor has begun work on the north side of the road. The contractor will be replacing some curbing and driveway approaches.

On Forest, the contractor has completed concrete work on the south side of the roadway. This week, the contractor will be re-locating a fire hydrant and begin curb removals on the north side later in the week.

On N Wilson, the contractor plans to begin work on the east side of the roadway, doing curb and driveway approach removals.

Phase 2 & 3 - Underground Work

The city's underground contractor will begin work on Etowah (Phase 2) and Wellesley (Phase 3) this week to install new storm sewer and catch basins, prior to the road contractor arriving on the blocks.

CAP2315 Phasing

CAP2335 Road Reconstruction


Parkdale (Vermont to N. Wilson)

The contractor will begin pouring the new roadway pavement this week.

Woodsboro

The contractor is finishing water service work this week and starting road pavement removals.

E. Hudson

The contractor has installed the new water main which is undergoing testing this week. Possible water main connection later in the week.

CAP2335 street list

CAP2302 Sidewalk Improvement Program

The sidewalk improvement program is tentatively scheduled to begin in June. Notices of Construction with estimates were mailed to property owners in April.

If you disagree with the estimate for sidewalk replacement adjacent to your home, you can call the engineering office to schedule an appointment to meet with the inspector for the project and review the sidewalk work.

picture showing target area for 2023

RCOC Greenfield & Normandy Roundabout

The Road Commission for Oakland County (RCOC) will be installing a roundabout at the intersection of Greenfield Road and Normandy Road this summer. The intersection will close when construction begins, the week of June 12th.

View the construction flyer

Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.

You can visit www.romi.gov/currentprojects to view the 2023 project map, find copies of mailed construction notices, and read about the city's various construction projects.