CAP2215 Asphalt Resurfacing
Contractor: Hutch Paving, Inc.
LANDSCAPE/LAWN RESTORATION: Lawn restoration is being delayed until end of August for more favorable temperatures for seeding.
Phase 1
Landscape restoration that didn't take or has not been completed will be delayed until Labor Day for more favorable weather.
Phase 2
For Delemere, the contractor plans to continue the new pavement striping this week. Landscape restoration to follow.
Phase 3
Troy, University, Fairgrove, Pingree and Alexander - Asphalt milling was completed last week. The contractor will be working on manhole and road base repairs this week. Troy and the west block of University is tentatively scheduled to receive the first layer of asphalt later in the week, with the remaining streets to follow next week.
Amelia - The contractor plans to install the first layer of asphalt on the block between Rochester and Blair mid-week. On the block between Blair and Campbell, the contractor is working on curbing and driveway approaches on the norths ide of the roadway, starting Tuesday.
Connecticut - The contractor will continue removal & replacement of concrete curbing and driveways this week.
Temporary 'No Parking' signs will be placed where room for construction equipment is needed.