Improving Royal Oak
2022 project map
modernize 75 logo

I-75 Freeway & Bridge Work


The following locations are closed this summer for reconstruction as part of the freeway project:

  • 12 Mile Road is closed at I-75
  • Gardenia Ave bridge
  • Lincoln Ave bridge

Questions or concerns regarding the bridge and freeway work should be sent to Oakland Corridor Partners who are overseeing Segment 3 of the construction for MDOT.

Call:    586.486.3626
Email:  info@ocp-i75.com

CAP2109 S Main Street and E Lincoln Avenue Resurfacing

Contractor: AJAX Paving Industries, Inc.


S. Main Street - Lincoln to 11 Mile

This week the contractor is continuing the new traffic signal underground work at Lincoln Ave. They will also continue work on sidewalk replacement and curbing.

FOURTH STREET ROAD CLOSURE: Beginning Monday the 16th, the contractor is closing Fourth Street to east/west traffic, so crews can pour the new intersection. This closure will remain in place for two weeks so the concrete can be installed and then cure to gain full strength. The intersection should be opened up in time for Memorial Day weekend.

E. Lincoln Avenue - Knowles to Campbell
Work on Lincoln Avenue is tentatively scheduled to begin towards the end of the month. Construction notices have been mailed and you can view the plans at www.romi.gov/roadwork

CAP2215 Asphalt Resurfacing

Contractor: Hutch Paving, Inc.


Phase 1

Inclement weather this week may delay the schedule, please be advised the below schedule is tentative based on good weather.

On Kenwood and Dorchester, the contractor will be milling the existing pavement this week with paving to follow by end of week.

Paving will be completed on Custer, Jeffrey and Sunnybrook this week.

Concrete work on Red Run Court is mostly completed with milling scheduled for mid-week.

Phase 2
On Vermont, the contractor will be pouring new concrete for the driveway approaches and remaining intersection work. New asphalt pavement is tentatively schedule for the end of the week/beginning of next week.

For Delemere, curbing and pavement removals begin this week.

DELEMERE ROAD CLOSURE AT NAKOTA: Delemere will be closed at Nakota Road to reduce cut-thru traffic and allow for construction operations. The road is open to LOCAL TRAFFIC ONLY. Traffic on Nakota Road can still go east/west through the intersection. The Delemere entrance to Normandy Oaks Park is also closed to reduce traffic. Visitors to the park should use the Nakota Road entrance on the north side of the park.

Phase 3
Since work has been progressing smoothly, the contractor may be able to start on some Phase 3 streets within the month, such as Alexander, University, Fairgrove and Pingree.

*Amelia and Connecticut will be started once the gas work on the block is complete. Consumers Energy Gas company has notified the city they will be starting end of May/beginning of June for the gas work.

Temporary 'No Parking' signs will be placed where room for construction equipment is needed.

Table displaying three phases with lists of streets underneath for each phase.

CAP2110 Northwood Viaduct Pavement Replacement

Contractor: FDM Contracting, Inc.


The city's contractor tentatively plans to begin construction the week of May 23rd. The contractor will be installing new water main and pavement underneath the railroad viaduct.

NORTHWOOD ROAD CLOSURE: Northwood will be completely closed to traffic at the viaduct. The closure will remain in place approximately five weeks while crews perform construction work. "Road Closed Ahead" signs will be placed along Northwood beginning at Woodward Ave to the west and Crooks Road to the east. However, residents may still see cut-thru traffic in their neighborhood due to the closure.

map showing closure limits

Consumers Energy Neighborhood Grid Projects


Consumers Energy is upgrading the gas pipeline infrastructure with some large neighborhood projects this summer, as shown in PINK & YELLOW on the project map above. To learn more visit: ConsumersEnergy.com/pipelineupgrade 

picture of worker digging
Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.

You can visit www.romi.gov/currentprojects to view the 2022 project map, find copies of mailed construction notices, and read about the city's various construction projects.